| 1.)
HISTORY
The first contacts for the
construction of a dry lignite coal grinding plant go back to January 1993.
LOESCHE GmbH presented the grinding technology to the "Energiewerk Schwarze
Pumpe AG" or ESPAG at that time.
In September 1993 LOESCHE
GmbH received the first enquiry from the "Lausitzer Braunkohle AG" being
the successor company of "ESPAG". During the tendering phase Dr. Gleisberg
was the contact person for the adjudication of the grinding systems for
lignite coal.
In the period from 1993 till
receipt of the final enquiry for two lignite coal grinding plants in December
1996 a multitude of meetings took place between "LAUBAG" and LOESCHE GmbH.
The final tender preparation
and submission took place at the end of February 1997.
|
2.) ORDER
AND BASE DATA
LOESCHE GmbH received the
order for the turnkey supply of a grinding plant consisting of two independent
mills for the production of pulverized lignite from LAUBAG, Senftenberg,
in July 1997. The LOESCHE partners for this order are:
-
Hoffmeier Industrieanlagen GmbH
& Co. KG, 59071 Hamm
-
ABB Automatisierungsanlagen
Cottbus GmbH, 03048 Cottbus
-
Walter-Bau AG, 02943 Boxberg.
The plant is to be erected in
"Schwarze Pumpe" in Brandenburg.
The order consists of the
complete engineering, including the submission of the authorization procedure,
civil structures, steel structures, mechanicals, electricals. process instrumentation
and control, erection and commissioning.
The complete plant is designed
for a continuous throughput of 92 t/h. Each mill is, however, is designed
for an output of 52 t/h. The guaranteed fineness of the
pulverized lignite is:
-
max. 0,4 % > 0,5 min
-
max. 8,0 % > 0,2 mm
-
and 25 - 40 % R DIN mm
The power consumption of
the plant is guaranteed at 16.4 kWh/t and the availability at minimum of
93 %.
|
3.)
PROJECT TIME TABLE
-
Effectiveness of contract July
22nd, 1997
-
Erection start of civil structures
Early November, 1997
-
Foundation stone laying December
12th, 1997
-
Erection start of steel structures
Early January, 1998
-
Erection start of mechanicals
Early January, 1998
-
End of erection August 3 1 st,
1998
-
Initial start-up and commissioning
September 1 st until October 2 1 st, 1998
-
Acceptance of turnkey project
by October 22nd, 1998 by LAUBAG
|
4.) BRIEF DESCRIPTION
OF THE TOTAL GRINDING PLANT
The grinding plants are supplied
with lignite directly (without intermediate storage) by up to four dryers.
-
The LOESCHE mills LM 28.2 D
with integrated classifiers grind, cool and classify the lignite coal in
one process step.
-
The product leaves the mill
via the classifier and is pneumatically transported to the bag filter and
collected.
The pulverized lignite is discharged
from the bag filter by screw conveyors and rotary valves. It is then fed
directly to the pneumatic conveying system and transported via a 600 m
long transport duct with diversion valves, to the two pulverized lignite
silos. The plants are being built to comply with the latest safety and
design regulations.
The patented LOESCHE process
"Grinding, Cooling and Classifying" in one process step, without intermediate
storage of the lignite coal, is the basis for the design of the grinding
plants.
|