The Central Milling System for the Steelworks 
in Taranto, Italy
 
LOESCHE GmbH, Duesseldorf
 
 
SUMMARY 
  
In March 1990, the consortium VAI, Kloeckner Stahltechnik, Italimplanti and LOESCHE GmbH received the turn-key contract for a pulverised coal injection and milling system to be erected in Taranto, Italy, site of the largest steelworks in Europe, from ILVA S.P.A., Genoa. 
  
The total investment cost is approximately 106,000,000 DM. The investment decision by ILVA S.P.A. was based on the following: 
  
• Partial refurbishment of the coke ovens would become unnecessary. 
• Savings in coke as a result of p.f. injection of up to 200 kg t/hot metal (HM). 
  
The state of the art thus permits economic advantages in the manufacture of pig iron in blast furnaces. 
 
 
   
The new plant shall supply the following blast furnaces, 
  
No. 2 6.000 t HM/d
No. 4 6.000 t HM/d
No. 1 6.000 t HM/d
No. 6 10.000 t HM/d
  
in the final phase of development, with 5,616 t/d of pulverised coal. 
  
Each of the three milling systems has a raw coal storage capacity of 470 tons and produces 80 t/h of pulverised coal. The pulverised coal is stored in five storage silos of 550 t capacity each. 
  
Each mill system is connected via drag chain feeder to the five storage silos. The total storage capacity (raw coal and pulverised coal) is 4,010 tons and represents 17.1 hours of blast furnace operation at the maximum pulverised coal injection rate. 
  
The above ensures a high availability of the total system. 
  
 The four members of the consortium are responsible for the following: 
  
* VAI, Linz, Austria: 
     Civil engineering for building foundations Civil  
     engineering for buildings and raw material silos  
     Building site, erection and erection supervision  
     Consortium leader 

* Klöckner Stahitechnik, Hamburg: 
     Responsible for the pulverised coal injection  
     system into the four blast furnaces 

* Italimpianti S.P.A., Genoa: 
     Supply of the foundations Supply of the buildings  
     and raw material silos Supply of high and low  
     voltage switch-gear Electricals for the entire  
     project.  Electrical cabling for the entire project  
     Installation of the high and low voltage switch-gear  
     as well as the electricals 

* LOESCHE GmbH, Duesseldorf: 
     Engineering Delivery of the machinery Milling  
     process control and control loops Erection  
     supervision Commissioning Training of the site  
     personnell for the three mill systems utilising the  
     largest tc date LOESCHE coal mills, type LM  
     28.325 D. 
  
  
Milling system technical data: 
  
Number of milling systems 3
Mill type: 3 x LOESCHE Roller Mill LM 28.325 D
Capacity (puleverized coal) 3 x 80 t/h
turn-down capacity per system (100-40%) 80 t/h, 100%;180.000 m³/h 
32 t/h, 70%;126.000 m³/h
Product fineness 20% R; 0,09 mm
Raw coal data  
Feed size 0-50 mm (max. 80 mm)
Volatile matter content 30 % maximum
Ash content 12 % maximum
Hardgrove index 45 °H
Surface moisture 12 % maximum
Chloride content less than 0,2 %
Heat source  
Blast furnace gas approx. 3.000 kJ/m³
Natural gas approx. 30.000 kJ/m³
Inert gas  
Nitrogen N2
Process gas CO2, N2, Steam an O2
  
  
Process data of one mill system: 
 
Output capacity 80 t/h
Product fineness 20%R; 0,09mm
Raw coal moisture 12%
Pulverised coal moisture less than 1%
Gas volume at mill outlet 180.000 m³/h
Temperature at mill outlet approx 95 °C
Dew point ot mill outlet approx 65°C
Oxygen content at mill outlet 9% (wet)
Gas volume at mill inlet 222.700 m³/h
Temperature at mill inlet approx. 320 °C
Dew point at mill inlet approx. 56°C
Exhaust gas volume approx. 75.300 m³/h
Exhaust gas temperature approx. 106°C
Dewpoint temperature of exhaust gases approx. 65 °C
Dust content of exhaust gases 10 mg/Nm³
Sound level 85 db (A) 1m
Mill Motor 950 kW
Specific power consumption at mill motor 11 kWh/t
Mill fan motor 950 kW
  
  
Scope of LOESCHE equipment supply 
 
3x1 Raw coal feed ststem
Drag chain feeder and associated auxiliary equipment, capacity 100 t/h
3x1 LOESCHE Roller Mill
Type LM 28.325D
Bevel gear gearbox  950 kW
Static integral mill separator
3x1 Fabric filter
Pulse Jet Filter
Gas volume 186.000 m³/h
Temperature 94-120 °C
Filter exit gas content 10 mg/m³ (dry)
3x1  Mill fan
Gas volume 205.000 m³/h
Temperature 94-120 °C
Mill fan motor P=950 kW
3x1 Pulverised coal transport system
3x1 Hot gas producer
with a heat generating capacity of  30 x 10^6 kJ/h
heating source bf gas approx 3.000 kJ/m³
3x1  Mill system duct work
with dampers and slides
3x1  Gas analysis system
for N2 and CO measurement
3x1  N2-Inertisation /safety system
3x1  Hoistung equipment
for service function on mills
3x1  Necessary motors
as well as electricals and control system
3x1  Necessary insulation
and equipment painting
  
 

The low and high voltage switch-gear as well as electrical control and analysis equipment is to be installed by Italimpianti to LOESCHE-Engineering specifications. 
  
The envisaged commissioning timetable is as follows: 
  • 1. Mill system: May 1991
  • 2. Mill system:  June 1991
  • 3. Mill system: July 1991
 
Description of self inertised grinding plant 
  
The raw coal is transported by conveyor belt from the raw coal stockpile to the coal milling system. The raw coal is distributed to the three raw coal silos which are cledusted by bag filters. 
  
Raw coal feed control to the mill is facilitated by a drag chain feeder. The drag chain feeder discharges into the centrally positioned (through separator) feed pipe. 
  
In the LOESCHE Roller Mill, raw coal is milled between the rotating grinding table and the rollers, by the application of pressure to the rollers. The grinding table is driven through a three-stage gearbox, where the grinding forces are absorbed by a segmented thrust bearing. In the absence of a material bed on the grinding table, contact between grinding table and rollers is avoided by accurately positioned buffers. The grinding forces to the rollers are generated by a hydropneumatic spring system. The grinding pressure is, within operating limits, infinitely variable, even during mill operation. The milled material is thrown outwards as a result of the grinding table rotation, where it is dried and classified by the gas flow through the louvre ring. The pulverised coal/gas mixture leaves the mill via the static separator. 
  
The mill is equipped with a sealed reject box for removal of foreign objects in the coal, such as tramp iron, bricks, steel wire etc.. 
  
A bag filter with a precollecting system and high pressure bag cleaning is employed for recovery of the pulverised coal from the mill gas stream. These modern filters are devoid of coal dust deposition areas and are therefore safe from smouldering coal fires. The filter is of a welded, sealed construction. The filter bags are cleaned cyclically by high pressure N 2 gas jets. This ensures that a consistent quantity and fineness of pulverised coal is transported via rotary valve, by the drag chain feeder to the fine coal storage. 
  
The mill fan delivers the required gas volume of approximately 186,000 m³/h for the mill system. The volume of gas is damper controlled. 
  
The drying of the coal employs hot gases of up to  
350 °C. To ensure that the temperature before filter exceeds 105 °C, a portion of the process gas is heated. The hot gas producer combustion chamber has a refractory lined muffle in which the flame achieves complete burn-out. 
  
A portion of the gas stream, consisting of combustion gas, in-leak and water vapour from drying, needs to be diverted from the mill system. A control damper after the mill fan facilitates this function. 
  
The pulverised coal from the fabric filter is transported via rotary valve and drag chain feeder to the pulverised coal storage. Each silo has a live volume of 1,200 m³. Measurement of CO at the top of the silos, and temperature measurements ensure a hazard free operation. N 2 gas is employed for inertisation of the silos. 
  
The mill system is operated as a self-inertised system by virtue of the process gases used. For start-up of the mill system, N2 flooding is employed as the initial inert atmosphere. 
  
The mill system warm-up procedures commence when the 0,2 content (wet) reaches 8 %.  
  
During normal operation, the inert atmosphere is derived from:  
  
* hot-gas producer combustion gases required for  
     drying  
* water vapour liberated during the drying /  
     milling process  
* N2 originating from the fabric filter cleaning system.  
  
During heated, non-production periods, N2 is available for system inertisation. 
  
The above holds also for the shutdown of the mill system. 
  
Technical data of entire system 
 
Blast furnaces
 
2
4
1
5
Blast furnace output (hot metal)
t/d
6.000
6.000
6.000
10.000
Furnace diameter
m
10,3
10,6
10,6
14,4
No. of injection points
pcs.
25
27
27
36
Injection rate
t/h
50
50
50
84
Total injection rate: t/h 234 
  
Raw coal silo 
Silo capacity:  
  • (moist coal): 3 x 470 t
  • (dry coal): 1,260 t
Pulverised coal storage 

Silo capacity: 5 x 550 t = 2,750 t 
Total capacity (pulverised coal): 4,010 t 
Operation time at full injection rate 200 kg/t HM: 17.1 h 
  

Mill system 
  
Mill type Vertical Roller Mill
Supplier LOESCHE
Mill size LM 28.325D
Grinding Table diameter 2.800 mm
Number of rollers 3
Number of mills 3
Capacity 3 x 80 t/h
Product fineness 20% R; 0,09 mm
Fine coal moisture less than 1,0 %
Mill motor 950 kW
Mill fan motor 950 kW
 
 
Injection system  
 
Supplier Kloeckner Stahltechnik GmbH
Pulverised coal storage silo 5 x 1.200 m³ (550t)
Pressure vessel 2 per  blast furnace
Number of blast furnaces 4
N2 consumption at full injection rate 14.180 Nm³/h
N2 presure 20 bar